Road Construction/Closings

Posted on: May 10, 2017

Prentice Street Reconstruction Project

Crews will begin underground work on Prentice St. at the intersection of Prentice & Fourth, working north to Maria. When that's complete, construction will continue from Prentice & Fourth south to College Ave.

Prentice St. will be closed to through traffic for the duration of the project, which should be completed by early October (weather permitting).

The project will involve replacing old sanitary sewers, storm sewers, water mains, and reconstructing the street including curb, gutter and sidewalks from Maria Drive to College Avenue.

Please slow down in construction zones and give our crews a BRAKE.

Stevens Point Transit's North Point route will be following this detour:

Bus Detour