Prentice St. Project Updates

The Prentice St. Reconstruction Project began Monday, May 15. The project is anticipated to be completed by early October. Letters to Residents have been posted to give information, answer questions, provide maps, and more.

  • Phase 2 of the project is underway. Utility work will be completed from College Avenue to Franklin Street by Thursday, June 22, at which point pavement removal is scheduled to begin with preparation of the foundation for the new road. 
  • The contractor is anticipating removing pavement and beginning utility work from Franklin Street to Fourth Avenue starting on Wednesday, June 21.
  • The project has progressed to a point where the contractor will be closing the Sixth Avenue and Prentice Street intersection to complete the utility work.
Resources
See the following documents for more information about this project:

To receive notices via email and/or text message whenever news stories regarding road construction and street closings are posted here, go to our Notify Me Module and sign up for the "Road Construction" News Flashes. News and announcements from this site are also posted on our Facebook Page and Twitter Feed.

Contact
Director of Public Works
1515 Strongs Ave.
Stevens Point, WI 54481
Ph: (715) 346–1561
Email

Office Hours 
Monday - Friday 
7:30 am - 4:00 pm

Visit the Project Page for More Info.