Road Construction/Closings

2 Stories
Posted on: June 21, 2017

Stevens Point Streets to be Chip Sealed

We will chip seal Wed., June 21 - Mon., June 26 (weather permitting): W. Zinda Dr., W. River Dr., Water St., Fourth Ave., Michigan Ave., North Point Dr., Streets except Michigan will remain open. Minimal delays can be expected during application.

See the Chip Sealing Map (pdf)
Posted on: June 20, 2017

Prentice St. Project Updates

The Prentice St. Reconstruction Project began Monday, May 15. The project is anticipated to be completed by early October. Letters to Residents have been posted to give information, answer questions, provide maps, and more.

  • Phase 2 of the project is underway. Utility work will be completed from College Avenue to Franklin Street by Thursday, June 22, at which point pavement removal is scheduled to begin with preparation of the foundation for the new road. 
  • The contrac...
Read More

Visit the Project Page for More Info.